On June 27, the Department of Transportation and Infrastructure had a meeting with the contractors who will build the box culverts.Four contractors are to build a total of eleven culverts on the road being climate proofed,. The first one will be finished by July and the last one is expected to be finished by January of 2014.

 
The contractors meet with DT&I Director, Mr. Luckymis, project engineer, Mr. Bahillo and FSM PACC Administrative Officer, Mr. Jose.